SERVICING OF 453 HIGH DENSITY RESIDENTIAL STANDS IN LUVEVE NORTH – BASE FORMATION FOR PHASE 2 ROADS
SERVICING OF 453 HIGH DENSITY RESIDENTIAL STANDS IN LUVEVE NORTH – BASE FORMATION FOR PHASE 2 ROADS
PROGRESS UPDATE
Phase 2 Road construction – 45%
Subgrade preparation and base formation completed – 1.3km of 2.7km
Road surfacing or bitumen application – 0km of 2.7km
Phase 2 Water reticulation – 66%
Pipe laying completed – 3703m of 4323m
Phase 2 Sewer reticulation – 69%
Pipe laying completed – 1153m of 2592m
Phase 2…